Time and Work
1. Basic Concepts
- If A can do a work in X days, A's 1 day work = 1/X
- If A's 1 day work = 1/X, A can finish work in X days
- If A and B can do work in X and Y days: Together = XY/(X+Y) days
- If A, B, C can do in X, Y, Z days: Together = XYZ/(XY+YZ+ZX) days
- If A is a times efficient than B and A finishes in X days: Together = aX/(a+1) days
- If A alone takes X days more than A+B together, and B alone takes Y days more: Together = √(XY) days
2. Pipes and Cisterns
- Inlet: Pipe that fills a tank
- Outlet: Pipe that empties a tank
- If a pipe fills in x hours: Part filled in 1 hour = 1/x
- If a pipe empties in y hours: Part emptied in 1 hour = 1/y
Net part filled in 1 hour = (1/x - 1/y)
Time to fill = xy/(y-x) hours (when y > x)
For pipes filling a tank with different diameters: The amount of water flowing is proportional to the square of the diameter.
3. Exercise (Questions 1-10)
Q1. A can complete a work in 12 days. A and B together can complete it in 8 days. In how many days can B alone complete the work?
- (a) 15 days
- (b) 18 days
- (c) 24 days
- (d) 28 days
Q2. I can complete one-third of the work in 8 days. In how many days can I complete that work?
- (a) 18
- (b) 12
- (c) 24
- (d) Cannot be determined
Q3. A can finish in 18 days and B in half the time. Working together, what part of work can they finish in a day?
- (a) 1/6
- (b) 1/9
- (c) 2/5
- (d) 2/7
Q4. A and B can finish in 10 days, B and C in 18 days. A worked 5 days, B 10 days, C 15 days finished remaining. In how many days could C alone finish?
- (a) 30 days
- (b) 15 days
- (c) 45 days
- (d) 24 days
Q5. Two pipes A and B can fill a cistern in 10 and 15 minutes. Both opened, but at end of 3 minutes, B turned off. How much time will the cistern take to fill?
- (a) 6 min
- (b) 8 min
- (c) 10 min
- (d) 12 min
Q6. A sum of ₹25 was paid for a work which A can do in 32 days, B in 20 days, B+C in 12 days and D in 24 days. How much did C receive if all work together?
- (a) ₹3
- (b) 16/3
- (c) ₹3
- (d) 17/3
Q7. Sunil and Pradeep can complete a work in 5 and 15 days. They both work for one day and then Sunil leaves. In how many days will remaining work be completed by Pradeep?
- (a) 11 days
- (b) 12 days
- (c) 15 days
- (d) 8 days
Q8. If 6 men and 8 boys can do work in 10 days while 26 men and 48 boys in 2 days, time taken by 15 men and 20 boys is:
- (a) 4 days
- (b) 5 days
- (c) 6 days
- (d) 7 days
Q9. I can complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete remaining work?
- (a) 2 days
- (b) 3 days
- (c) 4 days
- (d) 5 days
Q10. Three taps A, B and C can fill a tank in 12, 15 and 20 hours. If A is open all the time and B and C open for one hour each alternately, the tank will be full in:
- (a) 6 hrs
- (b) 6⅔ hrs
- (c) 7 hrs
- (d) 7½ hrs
4. Exercise (Questions 11-20)
Q11. 26 men can complete a work in 17 days. How many more men must be hired to complete in 13 days?
- (a) 9
- (b) 8
- (c) 6
- (d) 18
Q12. Work done by A in one day is half of B, and B is half of C. If C alone can complete in 7 days, in how many days can A, B and C together complete?
- (a) 28
- (b) 14
- (c) 4
- (d) 21
Q13. 16 men can complete a work in 8 days. In how many days can 12 men complete?
- (a) 10
- (b) 9⅓
- (c) 10⅔
- (d) Cannot be determined
Q14. A can complete a work in 12 days. A and B together in 8 days. In how many days can B alone complete?
- (a) 15 days
- (b) 18 days
- (c) 24 days
- (d) 28 days
Q15. 12 Men can complete one-third of work in 8 days. In how many days can 16 men complete that work?
- (a) 18
- (b) 12
- (c) 24
- (d) Cannot be determined
Q16. Computer A takes 3 minutes, B takes 5 minutes. A, B and C process average 14 inputs in one hour. How many minutes does C take for one input?
- (a) 10
- (b) 4
- (c) 6
- (d) 8
Q17. 21 binders can bind 1400 books in 15 days. How many binders required to bind 800 books in 20 days?
- (a) 7
- (b) 9
- (c) 12
- (d) 14
Q18. A and B can finish in 10 days, B and C in 18 days. A worked 5 days, B 10 days, C 15 days finished remaining. In how many days could C alone finish?
- (a) 30 days
- (b) 15 days
- (c) 45 days
- (d) 24 days
Q19. A is 30% more efficient than B. How much time will they take together to complete a job which A alone could have done in 23 days?
- (a) 11 days
- (b) 13 days
- (c) 20/17 days
- (d) None of these
Q20. Sunil and Pradeep can complete in 5 and 15 days. They both work for one day and then Sunil leaves. In how many days will remaining work be completed by Pradeep?
- (a) 11 days
- (b) 12 days
- (c) 15 days
- (d) 8 days
5. Exercise (Questions 21-30)
Q21. Two pipes A and B can fill in 15 and 12 hours. Pipe B alone kept open for 3/4 of time and both pipes for remaining. In how many hours will the tank be full?
- (a) 18 h
- (b) 20 h
- (c) 10 h
- (d) 13.5 h
Q22. If 6 men and 8 boys can do work in 10 days while 26 men and 48 boys in 2 days, time taken by 15 men and 20 boys is:
- (a) 4 days
- (b) 5 days
- (c) 6 days
- (d) 7 days
Q23. 12 men complete a work in 9 days. After 6 days, 6 more men join. How many days will they take to complete remaining?
- (a) 2 days
- (b) 3 days
- (c) 4 days
- (d) 5 days
Q24. Three taps A, B and C can fill in 12, 15 and 20 hours. If A open all time and B and C open one hour alternately, tank will be full in:
- (a) 6 hrs
- (b) 6⅔ hrs
- (c) 7 hrs
- (d) 7½ hrs
Q25. Two pipes A and B alone can fill in 36 and 45 min. Waste pipe C can empty in 30 min. A and B opened, after 7 min C opened. In how much time will tank be full?
- (a) 39 min
- (b) 30 min
- (c) 20 min
- (d) 36 min
Q26. A is half as good a workman as B and together they finish in 14 days. In how many days working alone will B finish?
- (a) 20 days
- (b) 21 days
- (c) 22 days
- (d) None of these
Q27. A can do 3/4 of a work in 12 days. In how many days can he finish 1/8 of the work?
- (a) 6 days
- (b) 5 days
- (c) 3 days
- (d) 2 days
Q28. A man is twice as fast as a woman. Together they do work in 8 days. In how many days each will do if engaged alone?
- (a) man-14, woman-28
- (b) man-12, woman-24
- (c) man-10, woman-20
- (d) None of these
Q29. 24 men working 8 hours a day can finish in 10 days. Working 10 hours a day, number of men required to finish in 6 days is:
- (a) 30
- (b) 32
- (c) 34
- (d) 36
Q30. A tyre has two punctures. First alone would make flat in 9 minutes, second in 6 minutes. How long does it take both punctures together to make it flat?
- (a) ½ min
- (b) 3½ min
- (c) 3⅗ min
- (d) 4¼ min
6. Exercise (Questions 31-59)
Q31. A man, woman or boy can do a job in 20, 30 or 60 days. How many boys must assist 2 men and 8 women to do work in 2 days?
- (a) 15 boys
- (b) 8 boys
- (c) 10 boys
- (d) None of these
Q32. If 15 women or 10 men can complete a project in 55 days, in how many days will 5 women and 4 men working together complete?
- (a) 75
- (b) 8
- (c) 9
- (d) 85
Q33. A can do in 10 days, B in 15 days. They work together for 5 days and rest by C in 2 days. If they get ₹450, how should they divide?
- (a) 225,150,75
- (b) 200,150,100
- (c) 250,100,100
- (d) 175,175,100
Q34. After working for 8 days, Anil finds only 1/3 work done. He employs Rakesh who is 60% efficient. How many more days will Anil take to complete?
- (a) 15 days
- (b) 12 days
- (c) 10 days
- (d) 8 days
Q35. X can do in 15 days. If joined by Y who is 50% more efficient, in what time will X and Y together finish?
- (a) 10 days
- (b) 6 days
- (c) 18 days
- (d) Data insufficient
Q36. If 12 men or 15 women or 18 boys can do work in 15 days of 8 hours, find how many men assisted by 5 women and 6 boys will finish same work in 16 days of 9 hours.
- (a) 6 men
- (b) 2 men
- (c) 8 men
- (d) 4 men
Q37. 2 men and 3 boys can do in 10 days while 3 men and 2 boys in 8 days. In how many days can 2 men and 1 boy do the work?
- (a) 12 days
- (b) 11 days
- (c) 15 days
- (d) 13 days
Q38. A man can do in 5 days but with son's help in 3 days. In what time can son do alone?
- (a) 6 days
- (b) 7 days
- (c) 7.5 days
- (d) 8 days
Q39. Pipe A can fill in 5 hours, B in 10 hours, C in 30 hours. If all open, in how many hours will tank be filled?
- (a) 2
- (b) 2.5
- (c) 3
- (d) 3.5
Q40. Two taps can fill in 12 and 18 minutes. Both open for 2 minutes and first turned off. In how many minutes more will tank be filled?
- (a) 15 min
- (b) 20 min
- (c) 11 min
- (d) 13 min
Q41. Fill pipe A is 3 times faster than B and takes 10 minutes less time. Find when cistern will be full if B only opened.
- (a) 20 min
- (b) 18 min
- (c) 15 min
- (d) 10 min
Q42. Three fill pipes A, B, C can fill separately in 3, 4, 6 minutes. A opened first, after 1 min B, after 2 min C. Find time when cistern full?
- (a) 2 min
- (b) 4 min
- (c) 3 min
- (d) None of these
Q43. Water flows at 3 m/s through pipe of radius 4 cm. How many hours to fill tank 40m×30m×8m?
- (a) 176.6 hours
- (b) 120 hours
- (c) 135.5 hours
- (d) None of these
Q44. 40 men can cut 60 trees in 8 hrs. If 8 men leave, how many trees cut in 12 hours?
- (a) 72
- (b) 60
- (c) 48
- (d) 36
Q45. 10 horses and 15 cows eat grass of 5 acres. How many acres will feed 15 horses and 10 cows, supposing a horse eats as much as 2 cows?
- (a) 40/7 acres
- (b) 39/8 acres
- (c) 40/11 acres
- (d) 25/9 acres
Q46. 4 pipes can fill in 15, 20, 30 and 60 hours. First opened at 6 am, second at 7 am, third at 8 am, fourth at 9 am. When will reservoir be full?
- (a) 11 am
- (b) 12 pm
- (c) 12.30 pm
- (d) 1.00 pm
Q47. Two pipes can fill in 14 and 16 hours. Due to leakage, 32 minutes extra taken. If cistern is full, in what time would leak empty it?
- (a) 110 hr
- (b) 112 hr
- (c) 115 hr
- (d) 100 hr
Q48. A tank is filled in 5 hours by pipes A, B and C. C is twice as fast as B and B twice as fast as A. How much time will A alone take?
- (a) 20 hrs
- (b) 25 hrs
- (c) 35 hrs
- (d) Cannot be determined
Q49. 12 buckets fill a tank when capacity is 13.5 litres. How many buckets needed if capacity is 9 litres?
- (a) 8
- (b) 15
- (c) 16
- (d) 18
Q50. A cistern has a leak that would empty in 8 hours. A tap admits 6 litres/min and it is emptied in 12 hours. The cistern can hold:
- (a) 7860 litres
- (b) 6840 litres
- (c) 8640 litres
- (d) 8840 litres
Q51. Rekha can do in 40 days. Surekha is 25% more efficient. Number of days taken by Surekha is:
- (a) 24 days
- (b) 28 days
- (c) 32 days
- (d) 35 days
Q52. A can do in 12 days and B in 15 days. If they work together for 6 days, fraction of work left is:
- (a) 1/4
- (b) 1/5
- (c) 1/10
- (d) 1/12
Q53. A alone can complete in 15 days and B alone in 20 days. Starting with A, work on alternate days. Total work completed in:
- (a) 17 days
- (b) 16 days
- (c) 14 days
- (d) 13 days
Q54. A alone can complete in 12 days and B alone in 48 days. Starting with B, work on alternate days. Total work completed in:
- (a) 18 days
- (b) 19 days
- (c) 19½ days
- (d) Data insufficient
Q55. 4 men can do in 10 days, 2 women in 15 days, 5 children in 12 days. In how many days can 8 men, 5 women and 15 children together complete?
- (a) 2 days
- (b) 3 days
- (c) 4 days
- (d) None of these
Q56. 48 workers can reap a field in 9 days. If work to be completed in 6 days, extra workers required are:
- (a) 36
- (b) 32
- (c) 24
- (d) 22
Q57. 4 men and 6 boys can do in 8 days and 6 men and 4 boys in 7 days. If daily wages of a boy be ₹20, what will be weekly wages of a man?
- (a) 280
- (b) 275
- (c) 270
- (d) 265
Q58. A is thrice as good as B and finishes 30 days less than B. Find time together.
- (a) 45 days
- (b) 11¼ days
- (c) 15 days
- (d) 22½ days
Q59. A takes twice as much time as B to do a work. Working together work completed in 8 days. A can do alone in:
- (a) 24 days
- (b) 12 days
- (c) 16 days
- (d) 28 days
Complete Answer Key
| 1. (c) | 2. (a) | 3. (a) | 4. (c) | 5. (b) |
| 6. (b) | 7. (a) | 8. (a) | 9. (a) | 10. (c) |
| 11. (b) | 12. (c) | 13. (c) | 14. (c) | 15. (a) |
| 16. (c) | 17. (b) | 18. (c) | 19. (b) | 20. (a) |
| 21. (c) | 22. (a) | 23. (a) | 24. (c) | 25. (a) |
| 26. (b) | 27. (d) | 28. (b) | 29. (b) | 30. (c) |
| 31. (b) | 32. (a) | 33. (a) | 34. (c) | 35. (b) |
| 36. (b) | 37. (a) | 38. (c) | 39. (c) | 40. (d) |
| 41. (c) | 42. (a) | 43. (a) | 44. (a) | 45. (a) |
| 46. (d) | 47. (b) | 48. (c) | 49. (d) | 50. (c) |
| 51. (c) | 52. (c) | 53. (a) | 54. (c) | 55. (d) |
| 56. (c) | 57. (a) | 58. (b) | 59. (a) |